Finland's TVO says nuclear reactor not ready in 2014


TVO said that the reactor being built in southwestern Finland known as Olkiluoto 3 would not be ready to produce electricity normally in 2014 as previously expected and that a new timetable had not been set, blaming its partners for the delay.

"The plant unit's installation works and plant automation system engineering under the responsibility of the supplier have not progressed according to the supplier's schedules," the Finnish company said in a statement.

 The European Pressurized Reactor (EPR) is the name for a new generation of nuclear technology, yet to be put into production.

TVO said that it was waiting for the construction companies working together in a consortium, Areva of France and Siemens of Germany, "to update the overall schedule and provide a new confirmation and analysis of the completion date as well as clarification of the measures needed to keep up with the schedule."

Monday's announcement marked only the latest in a string of setbacks for the construction project, which began in 2005, with the reactor initially supposed to begin producing electricity in 2009.

The Finnish EPR, which is an example of so-called third generation nuclear technology developed by Areva and which is set to have a capacity of 1,600 megawatts, was first delayed until November 2010, then to December 2011 and then to August 2014.

TVO said Monday that it was not satisfied with recurrent delays in the project but stressed solutions to various problems were being found one by one and work was progressing.