ATLANTA — America's first new nuclear plants in  more than a decade are costing billions more to build and sometimes  taking longer to deliver than planned, problems that could chill the  industry's hopes for a jumpstart to the nation's new nuclear age.
Licensing  delay charges, soaring construction expenses and installation glitches  as mundane as misshapen metal bars have driven up the costs of three  plants in Georgia, Tennessee and South Carolina, from hundreds of  millions to as much as $2 billion, according to an Associated Press  analysis of public records and regulatory filings.
Those problems, along with jangled nerves from  last year's meltdown in Japan and the lure of cheap natural gas, could  discourage utilities from sinking cash into new reactors, experts said.  The building slowdown would be another blow to the so-called nuclear  renaissance, a drive over the past decade to build 30 new reactors to  meet the country's growing power needs. Industry watchers now say that  only a handful will be built this decade.
"People  are looking at these things very carefully," said Richard Lester, head  of the department of nuclear science and engineering at the  Massachusetts Institute of Technology. Inexpensive gas alone, he said,  "is casting a pretty long shadow over the prospects" for construction of  new nuclear plants.
The AP's review of pending projects found:
—   Plant Vogtle in eastern Georgia, initially estimated to cost $14  billion, has run into more than $800 million in extra charges related to  licensing delays. A state monitor has said bluntly that co-owner  Southern Co. can't stick to its budget. The plant, whose first reactor  was supposed to be operational by April 2016, is now delayed seven  months.
— The long-mothballed Watts Bar power  plant in eastern Tennessee, initially budgeted at $2.5 billion, will  cost up to $2 billion more, the Tennessee Valley Authority concluded  this spring. The utility said its initial budget underestimated how much  work was needed to finish the plant and wasted money by not completing  more design work before starting construction. The project had been  targeted to finish in 2012, but has been postponed until 2015.
—  Plant Summer in South Carolina, expected to cost around $10.5 billion,  has seen costs jump by $670 million; but with lower interest rates and  cheaper-than-expected labor; the owners assert the project is still on  or under budget. A deadline to put the first new reactor online has been  delayed from 2016 to 2017; the second reactor is now eight months ahead  of schedule, targeted for early 2018.
No comments:
Post a Comment
This is an unmoderated blog. Please be professional and respectful as you post.