Friday, May 29, 2015

NRC Prepares for TVA’s New Nuclear Power Plant

Watts Bar 2
Watts Bar 2
May 28, 2015—As the Tennessee Valley Authority’s Watts Bar 2 project completes its transition from construction to operational readiness, the U.S. Nuclear Regulatory Commission has granted its Office of Nuclear Reactor Regulation the authority to issue a full-power operating license once it is satisfied that all regulatory requirements have been met.

TVA hailed the move toward the start-up later this year of the 1,150-megawatt reactor.

“The commission’s action was a critical regulatory step necessary to keep Watts Bar 2 on track to become the nation’s first new nuclear generation of the 21st century,” TVA Chief Nuclear Officer Joe Grimes said in a statement. “The delegation of this authority signifies confidence that NRC inspections show Watts Bar 2 is being built according to rigorous regulatory requirements and industry standards.”

Read more...

Wednesday, September 12, 2012

2 TVA nuclear plants shut down unplanned in August

Both of TVA's nuclear power plants in Tennessee had unplanned reactor outages of two days each in August.

The Chattanooga Times Free Press (http://bit.ly/RCSclA ) reported Unit 2 at the Sequoyah Nuclear Plant tripped on Aug. 16 when an electrical short occurred in one of the four nuclear coolant pumps.

The Watts Bar Nuclear Plant's only operating reactor shut down Aug. 28. TVA spokesman Ray Golden said human error caused the outage when an incorrectly calibrated testing device was plugged in.

READ MORE...

Read more here: http://www.sacbee.com/2012/09/11/4809288/2-tva-nuclear-plants-shut-down.html#storylink=cpy

Monday, July 16, 2012

Building costs rise at U.S. nuclear sites

July 15, 2012 12:00 AM

ATLANTA — America's first new nuclear plants in more than a decade are costing billions more to build and sometimes taking longer to deliver than planned, problems that could chill the industry's hopes for a jumpstart to the nation's new nuclear age.
Licensing delay charges, soaring construction expenses and installation glitches as mundane as misshapen metal bars have driven up the costs of three plants in Georgia, Tennessee and South Carolina, from hundreds of millions to as much as $2 billion, according to an Associated Press analysis of public records and regulatory filings.
Those problems, along with jangled nerves from last year's meltdown in Japan and the lure of cheap natural gas, could discourage utilities from sinking cash into new reactors, experts said. The building slowdown would be another blow to the so-called nuclear renaissance, a drive over the past decade to build 30 new reactors to meet the country's growing power needs. Industry watchers now say that only a handful will be built this decade.
"People are looking at these things very carefully," said Richard Lester, head of the department of nuclear science and engineering at the Massachusetts Institute of Technology. Inexpensive gas alone, he said, "is casting a pretty long shadow over the prospects" for construction of new nuclear plants.
The AP's review of pending projects found:
— Plant Vogtle in eastern Georgia, initially estimated to cost $14 billion, has run into more than $800 million in extra charges related to licensing delays. A state monitor has said bluntly that co-owner Southern Co. can't stick to its budget. The plant, whose first reactor was supposed to be operational by April 2016, is now delayed seven months.
— The long-mothballed Watts Bar power plant in eastern Tennessee, initially budgeted at $2.5 billion, will cost up to $2 billion more, the Tennessee Valley Authority concluded this spring. The utility said its initial budget underestimated how much work was needed to finish the plant and wasted money by not completing more design work before starting construction. The project had been targeted to finish in 2012, but has been postponed until 2015.
— Plant Summer in South Carolina, expected to cost around $10.5 billion, has seen costs jump by $670 million; but with lower interest rates and cheaper-than-expected labor; the owners assert the project is still on or under budget. A deadline to put the first new reactor online has been delayed from 2016 to 2017; the second reactor is now eight months ahead of schedule, targeted for early 2018.

Thursday, April 5, 2012

TVA ups Watts Bar reactor cost to $4.5 billion

Thu Apr 5, 2012 1:18pm EDT

* Reactor cost up from $2.5 billion estimate 
* Project was expected to start in 2012
* Bellefonte's new reactor likely also to be delayed

By Scott DiSavino
April 5 (Reuters) - U.S. government-owned Tennessee Valley Authority
(TVA) said on Thursday it now sees the new reactor at the Watts Bar 2
nuclear power plant in Tennessee online between September and December
2015 at a higher estimated cost of $4 billion to $4.5 billion.

In February, TVA said the 1,180-megawatt Watts Bar 2 project was
running over budget and behind schedule.

Watts Bar is one of five new reactors the industry expects to
complete by 2020 as part of a slow-moving nuclear renaissance in
the United States.

The others are the two reactors Southern Co is building at Vogtle
in Georgia and the two that Scana Corp is constructing at Summer
in South Carolina.

"Watts Bar Unit 2 remains a cost-effective solution for meeting
the region's base load power needs with clean energy at a
competitive rate," Tom Kilgore, TVA president and CEO, said in a
release.

"Even with the estimated added cost, Unit 2 at Watts Bar will still
be a competitive, reliable generation source for the people of the
Tennessee Valley," Kilgore said.

TVA decided in 2007 to complete the second reactor at Watts Bar to
help meet the region's growing demand for power. The unit was
expected to enter service in 2012 at a cost of about $2.5 billion.

"Our estimates on time and cost were wrong," Kilgore said.

"While our intentions were well founded, our execution and progress
reviews were not."

After TVA loads the fuel into Watts Bar 2, the company has said in
the past that it plans to start work to complete another reactor at
the Bellefonte nuclear site in Alabama.

TVA decided in August that it would complete the 1,260-MW Bellefonte
1 reactor. In the past, TVA said the project would cost about
$4.9 billion and could enter service by 2020.

The company has said it would take about six years of construction
time to finish Bellefonte 1, which was already about 55 percent
complete.

But the ultimate cost and timing for Bellefonte depends on work at
Watts Bar 2.

TVA started work on the Watts Bar and Bellefonte reactors in the 1970s
but put both projects on hold in the next decade due in part to a
projected decrease in power demand.

TVA has blamed the Watts Bar 2 delays in part on expected changes to
safety and other rules by the U.S. Nuclear Regulatory Commission
following last year's Fukushima nuclear accident in Japan.

Last month, TVA said that of the 900 contractors supporting the
Bellefonte project, it would cut 430 positions.

TVA said the contractors worked primarily for engineering firms,
including French nuclear conglomerate Areva SA , one of the main
companies involved in the project.

TVA did not disclose financial details about the job reductions.

Thursday, February 9, 2012

Delayed TVA nuclear plant gets new leaders

By Roger Harris

Posted February 9, 2012 at 4:27 p.m., updated February 9, 2012 at 6:48 p.m.

With construction of Watts Bar Nuclear Plant Unit 2 more than a year behind schedule and significantly over budget, TVA announced Thursday new leadership for the reactor project.

Coming out of retirement to head engineering and construction for Unit 2 is retired TVA executive Ike Zeringue.

The former president, chief operating officer and chief nuclear officer at TVA retired in 2005. Zeringue was the TVA executive who led the completion of Watts Bar Unit 1 in 1993.

TVA recently said Unit 2 will cost significantly more than the $2.5 billion originally budgeted and won't be completed until 2013, a year later than expected.

Installation of equipment is taking longer than originally planned, the agency said. The plant also has been hampered by safety incidents, including one in January that halted work by 1,000 employees and contract workers for three days when it was discovered that cables had been mistakenly removed from Unit 1 instead of being taken from Unit 2.

TVA launched a review of Unit 2 construction in August and expects to recommend a plan for finishing the project, including a new cost estimate, in the second quarter, said Mike Skaggs, TVA's senior vice president for nuclear generation, development and construction.

In addition to bringing Zeringue out of retirement, TVA is reassigning some existing nuclear executives.

Dave Stinson, previously vice president of construction at Watts Bar Unit 2, now is in charge of engineering, design and infrastructure planning at Bellefonte Nuclear Plant Unit 1 .

Ray Hruby, will move from Bellefonte to Watts Bar Unit 2 to manage overall project work, licensing, and safety.

The utility also said that when Bill McCollum, chief operating officer and president, retires in June, that position will not be filled.

In addition, the agency has eliminated a senior vice president position in its fossil power generation group. Robert Fisher, the executive who previously held that job, already has left TVA.

Other personnel changes are possible, according to the public utility. The management shuffle is intended to "align our strengths with our priorities" and "flatten the organization," Skaggs said in a telephone news conference with reporters.

The heads of TVA's nuclear and fossil divisions now will report directly to CEO Tom Kilgore.

The management shuffle is part of a broader organizational realignment the agency says will save money and reduce pressure on rates paid by consumers.

"We are aligning our business into functional teams focused on energy generation and energy delivery. Nuclear generation and construction will be separate groups reporting directly to the CEO. There should be no doubt as to the importance of nuclear in our energy mix," Kilgore said in a statement.

The energy generation organization will include coal, natural gas, renewables and hydroelectric power. The energy delivery organization will focus on delivery of reliable power to customers and the agency's relationship with distributors.