Friday, May 29, 2015

NRC Prepares for TVA’s New Nuclear Power Plant

Watts Bar 2
Watts Bar 2
May 28, 2015—As the Tennessee Valley Authority’s Watts Bar 2 project completes its transition from construction to operational readiness, the U.S. Nuclear Regulatory Commission has granted its Office of Nuclear Reactor Regulation the authority to issue a full-power operating license once it is satisfied that all regulatory requirements have been met.

TVA hailed the move toward the start-up later this year of the 1,150-megawatt reactor.

“The commission’s action was a critical regulatory step necessary to keep Watts Bar 2 on track to become the nation’s first new nuclear generation of the 21st century,” TVA Chief Nuclear Officer Joe Grimes said in a statement. “The delegation of this authority signifies confidence that NRC inspections show Watts Bar 2 is being built according to rigorous regulatory requirements and industry standards.”

Read more...

Thursday, January 8, 2015

TVA Asks Customers to Conserve in Light of Peak Power Demand

The Tennessee Valley Authority is asking for a voluntary reduction in electricity use until Friday
afternoon as a result of frigid temperatures causing high demand across the Southeast.

The request extends to all electric power consumers- residential, commercial and industrial customers.  The voluntary reduction will help ensure a continued supply of power to essential services throughout TVA's seven-state service territory and avoid interruptions of service.

All of TVA's available generating resources are being used to meet the peak power demand. TVA's bulk electric system remains secure and stable at this time.

'When it's below freezing, each time the temperature drops one degree another 400 megawatts of electricity is needed for our system,' said Jacinda Woodward, senior vice president of TVA Transmission and Power Supply.

'Setting your thermostat 2-3 degrees below normal this evening and Thursday morning can really help TVA manage the high power demand during this challenging time.'

A peak power demand is expected to happen Wednesday evening as regional temperatures are forecast to drop into single digits causing electricity demand to exceed 31,000 megawatts.

TVA says another peak demand will happen again Thursday morning with electric loads peaking around 32,400 megawatts.

Read more...

Thursday, October 2, 2014

Watts Bar Nuclear Plant shows it can perform under pressure

TimesFreePress - by Dave Flessner

Four decades after workers began construction of the Watts Bar Nuclear Plant, TVA successfully passed a critical test this week toward finally completing a second reactor at the Spring City, Tenn., power plant.

TVA workers and contractors on Tuesday successfully completed a cold hydro-static pressure test to ensure that key reactor equipment and systems did not leak or fail under pressure in the Unit 2 reactor under construction at Watts Bar.

"This is a significant milestone and success for Watts Bar yesterday to ensure that the workmanship used to construct the reactor coolant system and other associated systems were constructed in the right manner," said Ray Hruby, general manager for Watts Bar Unit 2 construction services.

Read more...

Wednesday, February 27, 2013

TVA signs contract for Clinch River mPower Construction Permit

The Babcock & Wilcox Company (B&W) (NYSE: BWC) announced today that its subsidiary, Babcock & Wilcox mPower, Inc. (B&W mPower), and the Tennessee Valley Authority (TVA) have signed a contract to prepare and support Nuclear Regulatory Commission (NRC) review of a Construction Permit Application for a B&W mPower™ small modular reactor (SMR) nuclear plant at TVA's Clinch River Site in Oak Ridge, Tenn.

“B&W thanks the State of Tennessee, Governor Haslam, Senators Alexander and Corker, Representative Fleischmann and the DOE”

This contract formalizes the first steps toward the anticipated B&W mPower deployment at Clinch River, as contemplated in TVA's May 2011 Letter of Intent to B&W for the project. It also represents the first definitive milestone in the U.S. Department of Energy’s (DOE) recently initiated SMR Licensing Technical Support Program for commercial demonstration of SMRs by 2022. The DOE selected B&W mPower in November 2012 as the recipient of the Program's competitively bid cost-share funding grant.

Read More...

Thursday, February 14, 2013

TVA seeks Sequoyah licence extension

The Tennessee Valley Authority (TVA) has applied to the US regulator to extend the operating life of its twin-unit Sequoyah nuclear power plant. If granted, the reactors could operate until 2040 and 2041, respectively.

The original 40-year licences for Sequoyah units 1 and 2 are due to expire in 2020 and 2021.

TVA submitted its operating licence extension applications to the Nuclear Regulatory Commission (NRC) on 15 January. The licence renewal process takes about 30 months andis expected to cost some $23 million, according to the utility.

TVA chief nuclear operator Preston Swafford commented, "By applying for a 20-year extension of our current operating licence now, we are affirming to the NRC that our plant is safe and in solid material condition." He added, "Extending the operating life of this nuclear plant supports TVA's vision to provide low-cost, cleaner electricity and a balanced energy portfolio."

Read More...

Wednesday, September 12, 2012

2 TVA nuclear plants shut down unplanned in August

Both of TVA's nuclear power plants in Tennessee had unplanned reactor outages of two days each in August.

The Chattanooga Times Free Press (http://bit.ly/RCSclA ) reported Unit 2 at the Sequoyah Nuclear Plant tripped on Aug. 16 when an electrical short occurred in one of the four nuclear coolant pumps.

The Watts Bar Nuclear Plant's only operating reactor shut down Aug. 28. TVA spokesman Ray Golden said human error caused the outage when an incorrectly calibrated testing device was plugged in.

READ MORE...

Read more here: http://www.sacbee.com/2012/09/11/4809288/2-tva-nuclear-plants-shut-down.html#storylink=cpy

Thursday, April 5, 2012

TVA ups Watts Bar reactor cost to $4.5 billion

Thu Apr 5, 2012 1:18pm EDT

* Reactor cost up from $2.5 billion estimate 
* Project was expected to start in 2012
* Bellefonte's new reactor likely also to be delayed

By Scott DiSavino
April 5 (Reuters) - U.S. government-owned Tennessee Valley Authority
(TVA) said on Thursday it now sees the new reactor at the Watts Bar 2
nuclear power plant in Tennessee online between September and December
2015 at a higher estimated cost of $4 billion to $4.5 billion.

In February, TVA said the 1,180-megawatt Watts Bar 2 project was
running over budget and behind schedule.

Watts Bar is one of five new reactors the industry expects to
complete by 2020 as part of a slow-moving nuclear renaissance in
the United States.

The others are the two reactors Southern Co is building at Vogtle
in Georgia and the two that Scana Corp is constructing at Summer
in South Carolina.

"Watts Bar Unit 2 remains a cost-effective solution for meeting
the region's base load power needs with clean energy at a
competitive rate," Tom Kilgore, TVA president and CEO, said in a
release.

"Even with the estimated added cost, Unit 2 at Watts Bar will still
be a competitive, reliable generation source for the people of the
Tennessee Valley," Kilgore said.

TVA decided in 2007 to complete the second reactor at Watts Bar to
help meet the region's growing demand for power. The unit was
expected to enter service in 2012 at a cost of about $2.5 billion.

"Our estimates on time and cost were wrong," Kilgore said.

"While our intentions were well founded, our execution and progress
reviews were not."

After TVA loads the fuel into Watts Bar 2, the company has said in
the past that it plans to start work to complete another reactor at
the Bellefonte nuclear site in Alabama.

TVA decided in August that it would complete the 1,260-MW Bellefonte
1 reactor. In the past, TVA said the project would cost about
$4.9 billion and could enter service by 2020.

The company has said it would take about six years of construction
time to finish Bellefonte 1, which was already about 55 percent
complete.

But the ultimate cost and timing for Bellefonte depends on work at
Watts Bar 2.

TVA started work on the Watts Bar and Bellefonte reactors in the 1970s
but put both projects on hold in the next decade due in part to a
projected decrease in power demand.

TVA has blamed the Watts Bar 2 delays in part on expected changes to
safety and other rules by the U.S. Nuclear Regulatory Commission
following last year's Fukushima nuclear accident in Japan.

Last month, TVA said that of the 900 contractors supporting the
Bellefonte project, it would cut 430 positions.

TVA said the contractors worked primarily for engineering firms,
including French nuclear conglomerate Areva SA , one of the main
companies involved in the project.

TVA did not disclose financial details about the job reductions.

Monday, April 2, 2012

Nuclear Energy Insider: Exelon, Progress Energy and TVA in crucial Power Uprate meeting

Huge challenges including time, cost, quality and procurement must be overcome when undergoing a power uprate project. With costs of uprating a unit at $250-500 million, creating a potential market of $25 billion, the US nuclear industry must have a clear understanding of the most effective methods to uprate nuclear power.

To advance the latest industry developments and learn from the first-hand experience of others, key utilities such as Exelon, Progress Energy, TVA, E.On will be meeting major OEM & EPC firms including Westinghouse, GE Hitachi, Shaw Power Group and Bechtel.

The conference they’ll be attending is undoubtedly the best chance in 2012 for service providers to meet and network with the major US utilities and vendors that are actively seeking new, innovative and practical solutions to aid their uprate projects.

Delivering expert case studies and focusing on specific issues such as engineering specifications for procurement and installation of major components during an Extended Power Uprate, this meeting is not to be missed. Attendees will benefit from:

  • An exclusive tour of the new Siemens Energy Turbine and Generator Manufacturing and Service Facility in Charlotte, North Carolina
  • Insight into the extended power uprate project at E.On’s OKG Oskarshamn 3 plant – now the world’s largest BWR – so you can develop schedules that save you time and money
  • An Operations & Engineering perspective of the Crystal River 3 uprate program from Progress Energy giving you the tools to improve your uprate strategy
  • Update on the Browns Ferry uprating program from the TVA giving you the facts on the latest opportunities and progress
  • Expert case studies from Bechtel's uprate work at Point Beach & St Lucie and analysis of the North Anna uprate project from ALSTOM

As well as comprehensive power uprate analysis from Exelon, Shaw Power Group, Westinghouse, GE Hitachi and more.

The 3rd Annual Nuclear Power Uprate Conference will supply your business with the critical intelligence and tools you need to understand effective uprating strategies. Delivered by the best in the industry – you’ll be able to take away key lessons and real world action points that you can implement to slash costs.

The conference will be bringing together 200 power uprate experts for two days of business critical intelligence, unrivalled networking and stimulating discussion. With senior level business leaders from across North America, leading contractors and equipment providers and specialist service companies – can you afford to miss out?

Thursday, February 9, 2012

Delayed TVA nuclear plant gets new leaders

By Roger Harris

Posted February 9, 2012 at 4:27 p.m., updated February 9, 2012 at 6:48 p.m.

With construction of Watts Bar Nuclear Plant Unit 2 more than a year behind schedule and significantly over budget, TVA announced Thursday new leadership for the reactor project.

Coming out of retirement to head engineering and construction for Unit 2 is retired TVA executive Ike Zeringue.

The former president, chief operating officer and chief nuclear officer at TVA retired in 2005. Zeringue was the TVA executive who led the completion of Watts Bar Unit 1 in 1993.

TVA recently said Unit 2 will cost significantly more than the $2.5 billion originally budgeted and won't be completed until 2013, a year later than expected.

Installation of equipment is taking longer than originally planned, the agency said. The plant also has been hampered by safety incidents, including one in January that halted work by 1,000 employees and contract workers for three days when it was discovered that cables had been mistakenly removed from Unit 1 instead of being taken from Unit 2.

TVA launched a review of Unit 2 construction in August and expects to recommend a plan for finishing the project, including a new cost estimate, in the second quarter, said Mike Skaggs, TVA's senior vice president for nuclear generation, development and construction.

In addition to bringing Zeringue out of retirement, TVA is reassigning some existing nuclear executives.

Dave Stinson, previously vice president of construction at Watts Bar Unit 2, now is in charge of engineering, design and infrastructure planning at Bellefonte Nuclear Plant Unit 1 .

Ray Hruby, will move from Bellefonte to Watts Bar Unit 2 to manage overall project work, licensing, and safety.

The utility also said that when Bill McCollum, chief operating officer and president, retires in June, that position will not be filled.

In addition, the agency has eliminated a senior vice president position in its fossil power generation group. Robert Fisher, the executive who previously held that job, already has left TVA.

Other personnel changes are possible, according to the public utility. The management shuffle is intended to "align our strengths with our priorities" and "flatten the organization," Skaggs said in a telephone news conference with reporters.

The heads of TVA's nuclear and fossil divisions now will report directly to CEO Tom Kilgore.

The management shuffle is part of a broader organizational realignment the agency says will save money and reduce pressure on rates paid by consumers.

"We are aligning our business into functional teams focused on energy generation and energy delivery. Nuclear generation and construction will be separate groups reporting directly to the CEO. There should be no doubt as to the importance of nuclear in our energy mix," Kilgore said in a statement.

The energy generation organization will include coal, natural gas, renewables and hydroelectric power. The energy delivery organization will focus on delivery of reliable power to customers and the agency's relationship with distributors.

LINK

Monday, February 6, 2012

Bellefonte Nuclear Plant reactor construction likely pushed back

SCOTTSBORO, Alabama - Construction running late on TVA's Watts Bar Nuclear Plant will likely cause a delay in construction of Bellefonte Nuclear Plant in Hollywood, The Scottsboro Daily Sentinel reported.

The newspaper said that Tennessee Valley Authority officials in a Friday conference call said Watts Bar near Spring City, Tenn., was expected to be completed late last year or early this year is only 70 percent to 75 percent complete. The completion "may slip out to late 2013 or into 2014," a TVA official said.

TVA can't begin construction on a reactor at Bellefonte until Watts Bar is completed, the paper reported.