Indiana Michigan Power, a unit of AEP (NYSE: AEP), has started the initial loading work for moving used fuel assemblies from the 2,107 MW Cook Nuclear Plant’s spent fuel pool into the recently completed dry cask storage facility.
Plans are to load 14 casks, each with 32 used assemblies. It takes about one week to load, seal, prepare and move one cask from inside the plant’s Auxiliary Building to the storage facility. The loading work is expected to continue until early November.
Cook has stored used fuel in a steel-lined concrete pool, but that pool is nearly full. Workers have expanded the storage capacity twice, but further expansion is not feasible.
The storage facility is a specially designed, two-acre concrete pad near the center of the plant property. The pad can hold 94 casks, which would support operation of both units through their current licenses of 2034 and 2037, and it could be expanded to ease removal of all fuel assemblies from the spent fuel pool and decommissioning of both units.
The casks are licensed by the Nuclear Regulatory Commission (NRC). The two-foot thick steel-reinforced concrete pad is surrounded by a double row of high security fencing. There is continuous electronic surveillance, daily direct observation and intervention response capabilities coordinated with local law enforcement. Compliance with NRC license radiation limits would result in no measurable difference in radiation levels at the plant boundary due to the dry cask facility. The facility will be isolated from public view and contact.
READ MORE...
Showing posts with label D.C. Cook Nuclear Plan. Show all posts
Showing posts with label D.C. Cook Nuclear Plan. Show all posts
Wednesday, August 1, 2012
Monday, May 7, 2012
Cook Nuclear Plant To Get Overhaul
BRIDGMAN, MI (WKZO} -- Talk about big money. At a cost of 1.7-billion dollars, the Cook Nuclear Plant in Berrien County is about to get a major overhaul, update and reconstruction.
I&M announced that its submitted a proposal to the Michigan Public Service Commission for a "Life Cycle Management Project" at Cook. Spokesperson Sara Bodner says that this is all intended to keep Cook running smoothly for the next couple of decades or so.
She says that I&M was given a 20 year license extension for Cook back in 2005, and this almost two billion dollar effort will ensure the facility is in top shape during that time. They'll be replacing equipment and components that are close to running their life cycle, and the work could take as long as eight years.
I&M announced that its submitted a proposal to the Michigan Public Service Commission for a "Life Cycle Management Project" at Cook. Spokesperson Sara Bodner says that this is all intended to keep Cook running smoothly for the next couple of decades or so.
She says that I&M was given a 20 year license extension for Cook back in 2005, and this almost two billion dollar effort will ensure the facility is in top shape during that time. They'll be replacing equipment and components that are close to running their life cycle, and the work could take as long as eight years.
Monday, April 30, 2012
Michigan: Reactor returned to service at Cook nuclear plant
Lake Township— Officials say a reactor at the Donald C. Cook Nuclear Plant in southwestern Michigan has been returned to service following a refueling outage that began in March.
The Herald-Palladium of St. Joseph reports the outage included installation of new transformers in addition to refueling the Unit 2 reactor, regular maintenance and testing. During the outage, about 1,000 contract workers supplemented the plant's regular 1,100-person staff.
The reactor returned to service on Saturday.
The plant is located in Berrien County's Lake Township. It's run by Indiana Michigan Power, a subsidiary of Columbus, Ohio-based American Electric Power Co.
The Herald-Palladium of St. Joseph reports the outage included installation of new transformers in addition to refueling the Unit 2 reactor, regular maintenance and testing. During the outage, about 1,000 contract workers supplemented the plant's regular 1,100-person staff.
The reactor returned to service on Saturday.