Showing posts with label Perry Nuclear Power Plant. Show all posts
Showing posts with label Perry Nuclear Power Plant. Show all posts

Monday, January 28, 2013

FirstEnergy's Perry nuclear power plant is back on line

PERRY -- The Perry nuclear power plant is making electricity again, following a five-day shutdown because of an electrical problem on the non-nuclear side of the plant.

Operators synchronized the reactor to the high-voltage grid late Sunday afternoon.  The reator is expected to reach full power later this week.

Perry automatically shut itself down early Tuesday morning after a blown fuse in the nearby turbine building cut power to pumps that push water into the boiling water reactor as needed when the reactor is operating. When this "feedwater" is interrupted, the plant automatically shuts downs, said Jennifer Young, spokeswoman for the FirstEnergy-owned reactor.

Engineers determined that the fuse had blown because of the cold temperatures in parts of the turbine building near a very large overhead door.  Maintenance teams have installed electric heaters in the area of the door while engineers figure whether a  more permanent solution is necessary.

Read More...

Friday, June 8, 2012

US nuclear output falls after Indian Point 2 in New York shuts

By Colin McClelland BLOOMBERG NEWS

 U.S. nuclear-power production fell for the first time this week after Entergy Corp.’s Indian Point Unit 2 in New York shut down and output slowed at FirstEnergy Corp.’s Perry reactor and Energy Northwest’s Columbia plant.

Generation declined 547 megawatts, or 0.6 percent, from yesterday to 85,342 megawatts, or 84 percent of capacity, according to filings with the Nuclear Regulatory Commission and data compiled by Bloomberg. Output was 1.7 percent below a year ago with 9 of 104 reactors shut.

Entergy’s Indian Point 2 reactor was at 1 percent of capacity today, according to the NRC. The unit automatically halted yesterday, and crews were investigating the main electrical generator as the “probable” cause, Jerry Nappi, a spokesman based at the plant, said then in an e-mailed statement. Nappi didn’t immediately reply to a call and e-mail seeking comment today.

The 1,020-megawatt unit on the Hudson River 27 miles (43 kilometers) north of New York City was at full power before it shut down at about 6 a.m. local time, he said yesterday. The 1,025-megawatt Unit 3 is operating at full capacity.

FirstEnergy lowered output from the 1,261-megawatt Perry nuclear reactor in Ohio to 60 percent of capacity from 100 percent to perform fuel integrity testing, quarterly turbine valve testing and a control rod pattern adjustment to improve reactor core performance, Jennifer Young, a spokeswoman at FirstEnergy based in Akron, Ohio, said in an e-mail today.

“The plant is expected to return to 100 percent power this weekend following the work,” Young said. The reactor is located on Lake Erie about 35 miles northeast of Cleveland.


Columbia Salmon

Energy Northwest reduced production by the 1,190-megawatt Columbia reactor, 10 miles north of Richland, Washington, to 85 percent of capacity from 100 percent. The unit periodically reduces output at the request of the Bonneville Power Administration because of high water levels on the Columbia River, according to John Dobken, a spokesman based at the plant.

Hydroelectric plant operators on the river try to avoid spilling water over their dams because that can increase nitrogen levels in the water and harm salmon, Dobken said. Instead, operators run the water through their power-generating turbines, which means less output is needed from the nuclear plant to meet demand, Dobken said.

Saint Lucie

NextEra Energy Inc. increased power from the 839-megawatt Saint Lucie 1 reactor in Florida to 48 percent of capacity from 3 percent. The unit shut June 3 after running at full output the day before.

Victoria Ingalls and Doug Andrews, company spokesmen at the plant 45 miles north of Palm Beach, said yesterday they were consulting with management before commenting.

Dominion Resources Inc. boosted output by the 799-megawatt Surry 1 reactor in Virginia to 30 percent of capacity from 1 percent. The unit shut May 7 until yesterday for refueling, Rick Zuercher, a company spokesman based near Richmond, said by e- mail at the time. The twin Unit 2 at the plant 17 miles northwest of Newport News is operating at full capacity.

Constellation Nuclear Energy Group LLC increased generation at the 1,140-megawatt Nine Mile Point 2 reactor in New York to 19 percent of capacity from 3 percent. The unit shut for refueling and maintenance from April 9 to June 5.

The 621-megawatt Unit 1 is at full power at the site 6 miles northeast of Oswego. Constellation Nuclear Energy is a joint venture of Constellation Energy Group Inc. and Electricite de France SA.

Susquehanna Boost

PPL Corp. raised power at 1,149-megawatt Susquehanna 1 reactor in Pennsylvania to 18 percent of capacity from 4 percent. The unit started June 5 after cracked turbine blades were found during a refueling and maintenance stoppage that began March 31, according to Joe Scopelliti, a company spokesman at the site.

The flaw, found on turbine blades for both units last year, prompted PPL to shut the 1,140-megawatt Susquehanna 2 on May 31 to inspect its turbine for similar wear, Scopelliti said. An engineering review hasn’t determined the cause of the cracking at the plant 50 miles northwest of Allentown, he said.

The Tennessee Valley Authority boosted the Browns Ferry 3 reactor in Alabama to 75 percent of capacity from 68 percent. The unit shut May 30 to June 3 after an electrical fault, according to the NRC.

Browns Ferry

Browns Ferry 1, which has a capacity of 1,065 megawatts, and Unit 2, with a capacity of 1,104, are at full power at the plant 84 miles north of Birmingham near the Tennessee line.

Progress Energy Inc. started the 900-megawatt Harris reactor in North Carolina after a refueling and maintenance halt that began April 20. The unit is at 6 percent of capacity.

Duke Energy Corp. is operating the 846-megawatt Oconee 3 reactor in South Carolina at 3 percent of capacity after planned refueling and maintenance that began April 13. The work included the replacement of an analogue reactor protection system with a digital version, Sandra Magee, a spokeswoman based at the plant, said then in a telephone interview.

Oconee 1 and 2, which also have capacities of 846 megawatts, are running at full power at the site about 30 miles west of Greenville.

Entergy’s Grand Gulf plant in Mississippi is operating at 1 percent of capacity. The 1,297-megawatt unit, located 25 miles southwest of Vicksburg, shut Feb. 19 for refueling and a fire was extinguished April 11 in the A main condenser.

Reactor maintenance shutdowns, usually undertaken in the U.S. spring or fall when energy use is lowest, can increase consumption of natural gas and coal to generate electricity. The average refueling down time was 43 days in 2011, according to the Nuclear Energy Institute.

LINK

Monday, March 12, 2012

Power Utilities Could Turn toPower Utilities Could Turn to Smaller Nuclear Reactors

The possibility of using small, modular nuclear reactors has FirstEnergy reconsidering its future in nuclear power, reports the Toledo Blade. In the mid 1980s, FirstEnergy spent $6 billion building the Perry Nuclear Power plant on Lake Erie, the paper reports, but the price tag kept the company from expanding.
However, the smaller reactors, which are only about the length of a bowling lane and cost as little as $500 million each, are making the Akron-based utility rethink its future in nuclear power.
Pete Sena, president of FirstEnergy Nuclear Operating Co., the utility's nuclear subsidiary, said while FirstEnergy can’t afford full-scale nuclear reactors, smaller reactors are manageable investments.
FirstEnergy is among 15 utilities who last year joined nuclear engineering and design firm Babcock & Wilcox Co. to form the mPower Industry Consortium. The group provides oversight and pre-licensing funding to develop a 125-megawatt "mPower" reactor — a small, modular light water reactor that is 83 feet high, weighs about 700 tons, and can power about 125,000 homes.
In comparison, the Davis Besse nuclear reactor, commissioned in 1978 near Toledo, generates about 940 megawatts.
The smaller reactors are more cost-effective for companies that must fund the cost of building their own plants, said Chris Mowry, president of Babcock & Wilcox's Modular Nuclear Energy subsidiary.
Since Ohio deregulated electric utilities in 2000, electric rates are determined through competitive bidding, and utility companies such as FirstEnergy can’t build new plants and have the cost passed on to customers.
The answer, Mowry said, is to get the total cost under $2 billion, or about the price tag of a new coal-fired or combined-cycle natural-gas fired plant.

With small, modular reactors, that $2 billion or less price is achievable, because for that amount, a utility should be able to buy two modular reactors with a total output near 360 megawatts, Mowry said.
The small modular reactors are still under development, and won’t be approved for use in the United States before 2020.