Wednesday, September 24, 2014
Florida nuclear power plant auctioning $100M worth of equipment
Wednesday, October 31, 2012
Nuclear power should be in Florida's portfolio
Read More...
Wednesday, October 3, 2012
Duke nuclear plant costs could top $3 billon: study
Sunday, August 26, 2012
Autumn nuclear power refueling seen up 5 percent year per year
That is roughly 4.9 percent, or 974 MW, above the 19,900 MW of nuclear capacity that was shut last year during mid-October, the height of the autumn refueling season, the data showed.
The data assumes units currently on extended outages -- like the San Onofre reactors in California and the Crystal River reactor in Florida -- will still be shut in mid-October.
Southern California Edison, the unit of California power company Edison International that operates San Onofre, said Unit 3 will not refuel as scheduled in October.
Due to the damage in Unit 3's steam generators, fuel will be removed from the reactor for the foreseeable future, SCE said in a filing.
"The current plan for Unit 3 is to de-fuel the reactor and place appropriate systems in a layup condition while analysis and testing continue given the uncertain timing of the likely repairs and restart," the company said.
A spokeswoman said a schedule to remove the fuel had not been determined. Nuclear fuel in Unit 2 was removed earlier this year. Unit 2 shut in January for refueling and inspections which revealed damage to its steam generators.
Neither San Onofre unit can return to service without the approval of the Nuclear Regulatory Commission. SCE is planning to cut staff at the plant before the end of the year.
Read More...
Thursday, May 3, 2012
Progress Energy says plan to fix nuclear plant coming soon
Bill Johnson, Progress Energy's president and chief executive, said during a quarterly conference call with investors Thursday that he is "very confident that we will start (repairs) by the end of the year, if the decision is to repair.''
Progress' insurer, the Nuclear Electric Insurance Limited, continues to balk at paying for damage to the plant's 42-inch-thick concrete nuclear containment building. Johnson made no mention of any alternative financing plan if the insurance does not pay.
"We have not yet received a definitive determination from NEIL about insurance coverage," Johnson said, echoing his repeated statements over the past six months. "Our negotiations with NEIL continue."
Customers will have to pay much of the more than $1 billion Progress is paying to replace the low-cost power the Crystal River plant used to generate.
The containment building cracked during a project to replace the plant's old steam generators. Progress decided to manage the project itself instead of hiring one of two firms that successfully handled similar projects at other plants around the country.
Thursday's conference call highlighted the numerous hurdles the utility faces over the next several months, including federal approval of its pending merger with Duke Energy and its hopes of rebounding from falling earnings.
Progress announced its net income for the first quarter of 2012 fell $34 million below the same period a year ago. The company reported its net income for the first quarter totaled $150 million, or 51 cents a share, compared to $184 million, or 62 cents a share, in 2011.
Johnson explained in a statement about the earnings that "the extremely mild weather through the first quarter of 2012 — although certainly a welcome respite for our customers — resulted in significantly lower energy sales in the Carolinas."
Despite that decline, Johnson and Mark Muhlhern, Progress' chief financial officer, spoke optimistically about Progress' prospects over the remaining three quarters of the year.
The company sees some "encouraging trends in growth and usage as the economy continues to heal," Muhlhern said.
Some of those signs were in Florida, where the company gained 11,000 customers in the first quarter, compared to 8,000 in the first quarter of last year.
But Florida is also where Progress faces some of its biggest challenges.
In addition to the broken Crystal River plant, the utility announced this week that it was raising the estimated cost of its proposed Levy County nuclear plant.
Progress now projects the plant will cost as much as $24 billion, up from the last estimate of $22.4 billion. When it was originally proposed in 2006, the project was expected to cost between $4 billion to $6 billion.
What may help Progress is its pending merger with Duke Energy.
Johnson said the utilities are working on an agreement with regulators in the Carolinas. Federal regulators also must approve the merger, but so far have twice rejected the deal.
The merger could play a key role in determining whether Progress' plan to build the two-reactor nuclear plant in Levy County ever materializes.
LINK
Wednesday, May 2, 2012
Progress says Florida Levy reactors delayed, cost up
* First reactor delayed to 2024 from 2021
* Cost estimate up to $19 billion-$24 billion
* NRC expected to issue license in 2013 to build Levy
By Scott DiSavino
May 2 (Reuters) - U.S. power company Progress Energy Inc's Florida utility has delayed the in-service date for the first reactor at the proposed Levy County nuclear power plant on Florida's west coast to 2024, with the second unit following 18 months later.
The company also boosted the cost estimate for the 2,200-megawatt Levy project to between $19 billion and $24 billion, it said in a statement.
Previously, the company said the first unit at Levy was expected to enter service in 2021 at an estimated cost of $17 billion to $22 billion.
Progress, based in North Carolina, said it pushed back the schedule and raised the cost estimate because of lower-than-expected customer demand, an economic slowdown, uncertainty over potential carbon regulation and low natural gas prices.
"Nuclear remains a key component of Progress's balanced solution strategy to meet customers' future energy needs," Vincent Dolan, president and CEO of Progress Energy Florida, said in the statement.
The company included the schedule and cost changes in its annual nuclear cost-recovery projections with Florida's utility regulator for the 2013 billing cycle.
In addition to the proposed new reactors, Progress wants to increase the output of the 860-megawatt Crystal River nuclear plant in Citrus County, near Levy.
Florida's nuclear cost-recovery rules, which are similar to regulations in other U.S. Southeast states seeking more nuclear power, allow utilities to recover development, construction and interest costs for new nuclear projects.
Georgia and South Carolina are using similar cost-recovery rules to encourage units of Southern Co and Scana Corp and partners to build new reactors in their states.
Utilities say the rules make reactor construction possible and help reduce customer costs.
Florida wants more nuclear power in part because natural gas fuels about 60 percent of the state's capacity, Progress said.
"Overdependence on any fuel can expose customers to fuel cost spikes and supply disruptions. (Florida's utility regulator) has cited the growing lack of fuel diversity in the state as a major strategic concern," Progress said.
Natural gas is cheap now, near a 10-year low of around $2.30 per million British thermal units, but over the past decade it has averaged above $6 and spiked to more than $15.
RATES TO RISE
If Florida regulators approve of Progress' request, the company said total nuclear cost-recovery charges would be $5.09 on a 1,000-kilowatt-hour (kWh) residential bill beginning with January 2013 billing, compared to $2.86 in 2012.
Progress said the 2013 breakdown would be $3.45 on a 1,000-kWh residential bill for Levy and $1.64 for Crystal River, up from $2.67 for Levy and 19 cents for Crystal River in 2012.
Progress said the Levy portion of the bill would be fixed at $3.45 through 2017.
Crystal River has been off line since September 2009, when a refueling and power up-rate began. During the upgrade, workers discovered a gap in the concrete containment dome, which was opened to install new steam generators.
Crystal River was originally expected to restart in April 2011 but Progress said last summer the unit would not restart until 2014. The company has estimated the cost of repairing the containment structure at between $900 million and $1.3 billion.
Last week, U.S. Nuclear Regulatory Commission (NRC) staff said in a final report that there were no environmental impacts that would preclude issuing construction and operating licenses for the proposed Levy reactors.
Progress expects the NRC will decide on the Levy licenses in early 2013.
Progress applied with the NRC in July 2008 to build and operate two Westinghouse Electric AP1000 reactors at Levy.
Westinghouse is majority-owned by Japanese multinational Toshiba Corp.
In January, Progress agreed to a $13.7 billion merger with neighboring North Carolina power company Duke Energy.
Duke is also seeking to build a nuclear plant at Lee in South Carolina and last summer signed a letter of intent to buy a potential stake in the Summer reactors being built by Scana and partners in South Carolina.
A spokeswoman at Duke, Rita Sipe, said the company could not speculate on whether a combined Duke-Progress would pursue both Lee and Levy since the companies had not completed the merger.
Sipe said Duke continued to develop the Lee site to ensure it remains an option in the future. She said Duke anticipates obtaining a license for Lee from the NRC in 2013.
Duke has not yet decided to pursue Lee, but it appears in the company's integrated resource plan as an option for the future to enter service around 2020-21. Several years ago, Duke estimated the Lee plant, which like Levy includes two Westinghouse AP1000 reactors, would cost $11 billion.
LINK
Thursday, March 1, 2012
Florida's Crystal River nuclear plant vexes Progress Energy
Progress Energy can congratulate itself for skirting major controversy at its three nuclear plants in the Carolinas in recent years. But 700 miles south of here, the Raleigh-based utility's nuclear plant in Florida is experiencing one of the most exorbitant and bewildering mishaps in the history of the nation's nuclear industry.
The Crystal River nuclear plant, on Florida's west coast, has been shut down since the fall of 2009 and is expected to remain off-line until at least 2014 - that is, if the company decides to resurrect the damaged facility at all.
The bill for repairs and replacement power could top $2.5 billion, and it's been unclear who - company shareholders or its Florida customers - will cover those costs since the utility's insurer stopped paying claims in mid-2011.
Read more here: http://www.bellinghamherald.com/2012/03/01/2416141/floridas-crystal-river-nuclear.html#storylink=cpy
The nuclear fiasco has no direct bearing on customers in North Carolina, because the Florida utility is operated separately from the Carolinas utility. But it could result in steep bill increases for the company's Florida customers, who already pay about $124 a month for power.
It could also dilute the benefits of Progress's pending $26 billion merger with Charlotte-based Duke Energy by introducing a costly liability. But Progress CEO Bill Johnson has told company employees in the past that the rationale for the merger is rising operating costs, including unforeseen financial calamities like the Florida setback.
"What's happened here is a first of its kind," said Florida Public Counsel J.R. Kelly, that state's consumer advocate. "There's nothing like this that's ever occurred in the world."
The problems experienced at Crystal River stem from a botched attempt to replace the plant's steam generator. The replacement required cutting a giant hole - measuring 23 feet by 27 feet - in the 42-inch-thick protective wall of the building that contains the nuclear reactor. To save money, Progress opted to manage the project on its own and awarded the contract to an engineering firm that had no experience in such repairs.
The work resulted in three instances of "delamination," a term used to describe an internal separation of the building wall. Each delamination is the size of a basketball court, said Florida's Deputy Public Counsel, Charles Rehwinkel. "They were definitely three separate events, or discrete incidents," he said.
The blunder shows that a highly experienced nuclear operator with a sterling reputation in the industry is not immune from a total breakdown in procedures that raise questions about judgment and competence.
The sequence of mistakes has put Progress in a state of crisis management for more than two years. Company officials are dealing with persistent questions from Wall Street analysts while they negotiate data requests from the insurer, Nuclear Electric Insurance Limited, known as NEIL.
The case rides on NEIL's decision whether it is obligated to pay up to $2.75 billion for repairs and replacement power under its confidential contract with Progress. Because NEIL was not expected to voluntarily pay the full coverage Progress sought last year, the utility suspended recording further insurance receivables in its corporate accounting statements. To date Progress has received $298 million in insurance payments, and the company stopped working on the Crystal River site last year to focus on refining its strategy and budget.
"We're not in a dispute yet," Progress CEO Bill Johnson told analysts two weeks ago. "We're still working positively and engaged with them on explaining what happened, what the repair plan is, and to make sure it's covered."
Earlier this year, Progress was able to avoid another dispute by reaching a rate settlement with Florida's consumer advocate, the Florida Public Counsel. That state agency had been building a negligence case against Progress to prevent the utility from passing on the repair and power costs to Florida customers. The Florida Public Counsel had conducted depositions with a dozen employees and contractors to expose errors and poor judgment, potentially leading to harmful disclosures that could have proved disastrous in Progress' negotiations with NEIL.
With the settlement done, Progress executives publicly express confidence that everything will work out. They say that NEIL, a pool created by the nation's nuclear operators, will ultimately agree to pay all claims, the full amount of which won't be known for several months. Kelly, the consumer advocate who wants to protect Florida customers from the staggering costs, agrees that the company is entitled to the insurance payments.
"It clearly was an accident," Kelly said.
The coverage from NEIL would make rebuilding the Crystal River facility the most economically feasible decision. It would prevent having to weigh whether to decommission the 36-year-old facility that provided about 8.5 percent of the electricity in Progress's Florida service area and its 1.6 million customers there.
It's not clear why NEIL has delayed payments, but Johnson said these cases can take months, and the Crystal River matter is by far the most complicated and costly NEIL has ever been asked to pay for. Johnson is a member of NEIL's board but as a matter of policy is not involved with the committee assigned to review Progress' claims, Kelly said.
NEIL, based in Delaware, declined to say what its biggest payout has been to date. According to news reports, NEIL declined a $200 million claim in 2007 to the operator of the Davis-Besse Nuclear Power Station in Ohio, but malfunctions at that plant were so serious that they resulted in criminal charges against company employees.
Read more here: http://www.bellinghamherald.com/2012/03/01/2416141/floridas-crystal-river-nuclear.html#storylink=cpy
LIN