SAN DIEGO (CNS) - Decommissioning of the idled San Onofre Nuclear Generating Station in northern San Diego County will cost an estimated $4.4 billion, according to a plan submitted Tuesday by majority owner Southern California Edison.
The plan was vetted in a series of public meetings. Another chance for the public to comment on the plan is scheduled for Monday at 4 p.m. at the San Juan Capistrano Community Center in that southern Orange County city.
The plan, summed up in three documents submitted to the Nuclear Regulatory Commission, envisions major decommissioning work to begin in early 2016. The documents include a decommissioning plan, a cost estimate and how to manage spent fuel.